We would likje to receive urgently offers factory in China
, Attached herewith are the following documents:
● Request for Quotation No. 93840
● Technical Specifications No. S-4306, S-4313, S-3535 and S-3518
● IDE General Terms and Conditions.
The following documentation will be required with the order:
1. Certified Drawings within 4 weeks from order.
2. Manufacturing Schedule within 4 weeks from order.
3. Quality Assurance Plan to be submitted within 4 weeks from order.
4. ITP (Inspection and Test Plan) within 4 weeks from order.
5. Monthly Manufacturing Progress Report.
6. Test certificates and technical documentation as per Technical Specs. requirements.
Delivery: Shipment 1 – 01/02/2011 – 25% of each item qty.
Shipment 2 – 15/05/2011 – 25% of each item qty.
Shipment 3 – 15/07/2011 – 25% of each item qty.
Shipment 4 – 01/01/2012 – 25% of each item qty.
Please review all attached documentation and follow requirements accordingly.